A Rehabilitation Schedule

EVENT DATE
Contract Awarded to Tidewater-Skanska
June 8, 2004
Begin Construction of Temporary Bridge
February 2005
Construction of Temporary Bridge
Approximately 1 1/2 Years
Rehabilitation of Bridge of Lions
Approximately 3-4 Years
Removal of Temporary Bridge
Approximately 10 Months
Anticipated Completion Date
2010

 

 