ST. AUGUSTINE – Five days of daytime channel closures are scheduled August 11-15, 2008 beneath the Bridge of Lions and adjacent temporary bridge. Two openings will be provided each day during the closures. Details of the closure times and openings are as follows:
| DATE |
TIME |
BRIDGE OPENINGS |
Monday - Friday,
August 11-15, 2008 |
Channel Closed 7:00 a.m. until 8:00 p.m. |
Openings provided at:
1:00 p.m.
1:30 p.m. |
To travel through the bridge during one of the scheduled openings, mariners must radio the bridge tender on marine radio channel 9.
These closures have been reviewed and approved by the U.S. Coast Guard. For more information, please call (904) 825-3647 or (904) 669-1165.
The Bridge of Lions Rehabilitation project, funded by the Florida Department of Transportation (FDOT), began in February 2005 and is expected to last approximately five years, excluding potential weather delays. For more information regarding the bridge rehabilitation, please visit our website at www.FDOTBridgeofLions.com or contact Laurie Sanderson in the public information office at (904) 825-3647 or at info@FDOTBridgeofLions.com.
|